"Opinions" of the State Grid
distributed only solve the problem of whether the grid, and online electricity
transmission As for and how to measure, how the balance sheet per kilowatt to
how much money, is not mentioned. Discussed with the national network of
internal grid hinder eliminate the biggest obstacle for the power plant
investors is the approval of the power plant. This problem does not lie in the
power grid, but the Development and Reform Commission.
According to the State Council in 2004, the
government approved investment project directory, energy power plant project
investment and construction projects need to obtain the approval of the
relevant government departments, including the provisions of the wind power
plant is: a total installed capacity of 50,000 kilowatts and above projects
invested by the State Council approved by the department in charge of the rest
of the project by the approval of the investment department of the municipal
government. This "catalog" First PV power plant (Of course, 2004 the
PV small solar panels also no rise), the provisions following 50MW wind power plant project need
Municipal Development and Reform Commission approved only. Let us think less
than 50MW PV power plant projects also need the approval of the Municipal
Development and Reform Commission.
Documentation requirements, approved the
project application report prepared by the engineering consulting agencies have
Class A qualification a 5 copies ", about 20 million a Class A
qualification understand the project application report, but also urban
planning, environmental assessment, land, etc. approval report. All the reports
are down, estimated at 500,000. Usually only 50 million of the total investment
of a 50KW distributed PV power plant, a the 3KW distributed photovoltaic power
station can basically meet the daily demand for electricity in an ordinary
household. Such a high approval costs and cumbersome approval procedures, this
is not a joke?
Obviously, this the approved directory has
been unable to adapt to the requirements of the distributed development of new
energy. The original project approval procedures for corporate investment in
large-scale investment in energy projects. As ordinary residents of distributed
photovoltaic power plants, not legal. Influence city planning does not affect
land use, housing is their private property rights does not affect the
environment, should be approved by the Development and Reform Commission, the
project is not required to establish in their own roof. The NDRC projects
approved policy should advance with the times, and make the appropriate
adjustments and clarifications:
A government approved investment in the
project directory of photovoltaic power plants, and clear photovoltaic solar panel price power
plant approval thresholds and approval authority approval authority. 2.
Development and Reform Commission approved the policy should be and the State
Grid and Deal matched. Since the State Grid allows 6MW following distributed
grid waive access fees, the NDRC approved should be adjusted accordingly 6MW
distributed PV projects need project approval 6MW distributed PV project filing
system instead.
The project approved part of the approval
of power plant construction. Currently, a power station from the application
for the project to the final grid, in the middle after project approval,
flagging, feasibility study, environmental assessment, planning, and network, the
key aspects of the land permits, security, acceptance, involving at least nine
government organs and departments (including grid), to cover the 48 chapters
(or license), a long way off. This is brutal domestic PV power plant investors
now face administrative environment.
Too many approval links, rent-seeking,
corruption, delays in business opportunities, the arrival of a huge additional
burden to investors. Approval policy in the end is to promote the development
of new green energy or block its development? Or is as an excuse to promote the
development of new energy and fertilizer private pockets? To promote the
development of the PV terminal market, we need to simplify the administrative
examination and approval procedures, and clear the obstacles on the project
approval, and completely remove the doubts of the power plant investors.