WASHINGTON Taizhou Medical Hi-tech Zone,
reporters on the 20th came to see the 10 plant roofs covered with blue
photovoltaic cells from a tall building, and even up to become an installed
capacity of 1.28 MW photovoltaic power station, before the Spring Festival on
the grid vote annual generation of 1.5 million kwh.
Last November, after the introduction of
small-scale photovoltaic power plants free grid Deal, photovoltaic power plants
and process is greatly simplified, more photovoltaic power plants in our
province to speed up the progress of construction. Recently for more than two
months, only the intention of building photovoltaic power plants under
construction in Taizhou there are more than 10. "Song Jianhua, general
manager of Taizhou Power Supply Company introduced.
These photovoltaic power solar panel plants were built
in the roof, not an area not affect the building the appearance of low
construction costs, can also play a PV "dispersed development nearby use
of" advantage. Jiangyin the Complex Core photovoltaic technology companies
project manager Yao Su Jian introduced recently the company photovoltaic power
plants in a shipyard in Jingjiang formal power generation, with 30,000 square
meters plant roof, the annual generation of 5,000,000 kwh.
It is reported that the country has just
approved the second batch of "Golden Sun" demonstration project, the
province harvested 26 demonstration projects, the number of items and installed
capacity ranks first, most of the roof power station. The province will also
introduced policies to encourage units, communities and households to install rooftop
PV power plant.
Recently, Chint Golmud PV power plant two
20MW project passed Qinghai Electric Power Company grid acceptance, and
acceptance of Qinghai Development and Reform Commission, the organization of
the project, approved grid tariff.
The Chint Golmud 20MW a project is a large
ground-based power plant, approved last year, the first grid Qinghai-grid
tariff of 1.15 yuan. After about a year of operations at the same time, the
generating capacity of the power plant in the solar cell power plant in the same
area is relatively high, monthly energy output of about 3.4 million.
The two smooth grid thanks to the strong
support of local leaders and Chint project team to play an active goal
enterprising spirit, at the same time to ensure the progress of the project to
ensure the quality of the entire project. In another development, Chint in
Gansu Yongchang 100MW, and Axel 10MW project will officially put into operation
recently.
Ultra-day sun is brewing production lines
relocated to Luoyang , Henan
Province, and Jiujiang , Jiangxi ,
Qinghai , and Shanghai production line but also a little
exports compared to the two production lines almost no exports, production at a
standstill. "Shanghai one works in a bank sources said.
He said, to move out of all the production
equipment, or further exacerbate and contradictions between local banks, Nikai
Lu went to Luoyang
and local banks have recently consultation. "At present, Luoyang local
bank loans overdue, super day solar charge controller sued the court and seized part of the
ultra-Day Luoyang assets, at the same time, the ultra-Day is still communicate
with the creditor banks such as Everbright and CITIC."
"The only waterfront on photovoltaic
power plants, in order to start the components of demand, and thus boost the
number of PV upstream component production." Insiders said,
"countries will be introduced on subsidies and support specific policies
of the PV power plant." It is understood that, Recently, the government is
in contact the person in charge of many PV companies, research some
market-oriented approach to boost the construction of photovoltaic power
plants, programs including the photovoltaic industry fund.